Project description | Construction and operation of new thermal power generation and desalination plants in Ras Laffan Industrial City Generating capacity: 2,730 MW (GTCC), Desalination capacity: 290,000 tonnes of water a day |
---|---|
Project duration | 25 years after commencement of plant operation |
Schedule | April 2011: Full operation started |
●First time our company participated in an overseas IPP project
●Largest power generation and desalination project in Qatar
●Sent engineers to the site during the project’s startup period
Between August 2009 and April 2012, sent multiple engineers, including a maintenance manager and assistant manager, to the site and constructed the project’s maintenance system